Calculating the amount of late payment compensation

This option only applies to contracts formed on or after the 7th August 2002. For these contracts, in addition to interest the supplier may also charge an amount to compensate for the costs of collecting late payments.

The amount of compensation that can be claimed is determined by the amount outstanding as follows:

Amount OwedCompensation
up to 999.99 pounds40 pounds
1000 to 9999.99 pounds70 pounds
10000 pounds and over100 pounds